1st Avenue Lighting Project Phase II

Bid letting Date & Time:
28 September 2011 2:00 pm  Aldermen's Chambers/City Hall
Low Bid: J.F. Edwards Construction Company/Geneseo, IL.
$389,492.00 estimated completion May 2012
December 2011 construction began

17th Avenue Water Tower Repaint

Bid letting Date & Time
12 January 2012  2:00 pm Council Chambers
Apparent low bidder was JETCO with a
Low base bid of $261,800

16th Street Sewer Main Extension

Bid letting Date & Time
26 January 2012  2:00 pm Council Chambers
Apparent low bidder was Miller Trucking & Excavating with a
low bid of $72,500.

                                    construction